| |
 |
|
 |
 |
 |
1818 |
|
John Blenkinsop / Krigar
Saarland Rack Locomotive |
 |
 |
 |
Even before the trials of the Chorzow locomotive it was decided to construct another larger Blenkinsop type locomotive with cylinders 10 inches in diameter. This was for use in the mining area of the Saarland. The locomotive was built at the Royal Ironworks in Berlin supervised by Krigar and sent for tests on 22nd September 1818 to the Geislautern ironworks between Saarbrucken and Saarlouis.
The locomotive arrived at the ironworks in pieces on 4th February 1819. The ironworks had to construct a rack railway for it to be tested on but delays occurred due to problems in making the rails match the sample sent from Berlin. Eventually the Mining Inspector, de Berghes, reported trials on 25th September when he was said it was working very unsatisfactorily.
On 31st October 1821, de Berghes summarised the experiments and described the locomotive and its defects. The engine consists of a wooden chassis, carried on four wheels with concave wheel rims. A cast iron boiler with a tubular firebox created the steam for two 10 inch cylinders, one behind the other. The pistons drove two small gear wheels by means of crossheads and two connecting rods. They in turn drove a large gear wheel situated on one side of its own axle. This is situated close to the rail in order to mesh with the teeth on the rail and thus move the engine.
He described the motion as being unsteady, stumbling and precarious and the regulator as being complicated as it was constructed from a four-way cock, which did not allow starting and stopping to be controlled accurately. Another major defect was that the water reservoir, which consisted of a small bucket, quickly became empty.
De Berghes rectified the water reservoir defect and trials were organised for 22nd March 1822 when in front of officials the boiler was lit and with a pressure of 40 lbs per square inch the regulator was opened but it took several attempts to get it moving down a slopping track. When the regulator was altered it came to a stop and would only move a few revolutions with the help of four to six men. By this time steam was escaping from the joints and stuffing boxes and the pistons were binding. Although further attempts were made that day, and the next, they failed to get the locomotive to work. The officials expressed the opinion that the parts were badly made.
Krigar protested at the result of the trial so they were repeated but with the same results. The main reason stated was the poor fit of the pistons, which allowed large amounts of steam to pass, causing great steam wastage. The locomotive was abandoned at Saarbrucken until in 1834 it was suggested that it was dismantled. It was then decided to auction it off instead but the bids were too low. Eventually it was sold on 18th January 1837 for the equivalent of £46. |
 |
 |
 |
 |
|
 |
|
 |
The geography of the area meant that the route of the railway had to go over a hill 330 feet high and this section was worked by a combination of five self-acting inclines and two 60 hp stationary engines were used to haul the wagons up the others.
The flat sections were worked at the time of opening by three of George Stephenson's steam locomotives. These followed the Killingworth design having two cylinders sunk into the top of the boiler with cross beams driving connecting rods which drove down on the wheels by via crank pins. These locomotives had four wheels coupled by chain and had steam suspension. They were named Dart, Tallyho, and Star after local racehorses.
At the opening of the railway on 18th of November 1822 crowds of people came to see this new marvel. They witnessed the locomotives pulling seventeen loaded wagons, averaging sixty-four tons, at the rate of four miles an hour.
Experiments were carried out at the colliery in 1828 when it was worked out that the daily expense of two locomotives worked out at £2 - 9s - 2d compare to the £6 it would cost to use horses to perform the same amount of work. During these experiments two locomotives hauled 1,759 tons and 112 cwt. a distance of 2,541 yards.
|
 |
 |
 |
 |
 |
One of Stephenson's locomotives showing later additions of plate springs and coupling rods.
|
 |
 |
|
 |
|
 |
The locomotive did not have any springing, but the rear axle was carried in a tube, which acted as an axle box. This was pivoted at the centre to allowing the axle to rock thereby giving a three-point suspension. This was a replacement for the steam suspension, which by this time was considered too complex.
The locomotive had four cast iron wheels, each with eight spokes. One of these broke only a few days after the opening of the railway, which resulted in everything having to be hauled by horse. The cast iron wheels were later changed for two-piece cast iron plug wheels.
Locomotion weighed 6.25 tons empty and 7.75 tons full when built.
Locomotion was the first locomotive delivered to the railway in September 1825 and it hauled the opening train on 27th September 1825.
Three further locomotives to this design followed; Hope November 1825 Black Diamond April 1826 Diligence May 1826
Locomotion worked regular on the S & D until 1840. In June1846 it was used for the opening of the Redcar line and from 1850 it was used to pump water at a west Durham colliery where it stayed until 1857 when the Pease family presented it to the Stockton and Darlington Railway for preservation. |
 |
 |
 |
 |
|
 |
|
This concludes my brief history of locomotives up to 1825. I will update this text again if I get further information. |
|
|
|